- Home
- Government
- City Enhancements
- Main St Complete Streets Construction
- Project Schedule & Progress Reports
Project Schedule & Progress Reports & Photo Gallery
-
Pavement Striping Operations
-
Street Tree planting operations
-
Railings at elevated sidewalk at Auburn Avenue
-
I-beams for East Gateway Signs
-
East Gateway Signs with luminaires
-
Light Poles installed between Locke and Auburn
-
Storm Drain piping on S. Behrend
-
S. Miller and Main Street looking west at dusk
-
Asphalt operations on S. Allen Avenue
-
Asphalt operations on S. Locke Avenue
-
Roadway grading on S. Behrend Avenue
-
Railings on S. Locke Avenue
-
Brick paver area near Behrend roundabout
-
Asphalt on S. Behrend Avenue
-
I-beams for West Gateway Signs
-
New double center stripe - looking east on Main Street at Behrend
-
New double center stripe - looking west on Main Street at Behrend
-
Base layer of Asphalt at Auburn Avenue
-
Commercial Driveways
-
Assembling the Light Poles
-
Curbing and Gutters on Main Street at Allen Avenue
-
Irrigation and Electrical conduits
-
Storm Drain manhole on S. Behrend
-
Orchard Park Plaza new brick walkway
-
Subsurface Stormwater Reservoir #4 on N. Allen Avenue
-
New Furnishings
-
Pavement Markings and Crosswalks
-
Paving Orchard Avenue Roundabout
-
Railings
-
Breezeway Plaza Steps and Ramps and Railings
-
Orchard Avenue Roundabout
-
Main Street and N. Wall Avenue at Night
-
Night Time Aerial of S. Miller Roundabout
-
Asphalt placement at Orchard
-
Grading Operations for Asphalt
-
Asphalt Milling Operation
-
Decommissioning Traffic Signal at Behrend Avenue
-
ADA ramp in front of TJ's Diner
-
Sidewalk and planters near Dusty Attic
-
Sidewalk and planters near Orchard Park
-
S. Miller roundabout median island
-
S. Miller roundabout apron
-
S. Miller roundabout and brick pavers
-
Boulder Feature at Roundabout
-
Asphalt Milling Operations
-
Concrete Removals
-
Evening looking east
-
Crane Removing Traffic Signals at Orchard
-
Water Line Installation
-
Storm Drain Manhole on S. Commercial Avenue
-
Subsurface storm water reservoir on S. Commercial Avenue
-
Raised Planter Boxes
Due to change orders which have increased the contractor’s scope of work, additional work days have been added to the existing contract. However, the contractor is on target for substantial completion in November 2020 since most of this additional work can be accomplished while roads and sidewalks are open to vehicles and pedestrian traffic. This work could include finalizing the streetscape improvements, such as installing landscape features, site furnishings and amenities, signage, and other design elements.
Project Schedules:
Project Schedule - Updated 05/07/2020
Project Schedule - Updated 04/01/2020
Project Schedule - Update 02/27/2020
Project Schedule - Updated 02/06/2020
Project Schedule - Updated 01/27/2020
Project Schedule - Preliminary 01/06/2020
Stay up-to-date with the project with these weekly reports.
Project Progress Summary - Week 50 - December 16, 2020
Project Progress Summary - Week 49 - December 9, 2020
Project Progress Summary - Week 48 - December 2, 2020
Project Progress Summary - Week 47 - November 23, 2020
Project Progress Summary - Week 46 - November 18, 2020
Project Progress Summary - Week 45 - November 11, 2020
Project Progress Summary - Week 44 - November 4, 2020
Project Progress Summary - Week 43 - October 28, 2020
Project Progress Summary - Week 42 - October 21, 2020
Project Progress Summary - Week 41 - October 14, 2020
Project Progress Summary - Week 40 - October 7, 2020
Project Progress Summary - Week 39 - September 30, 2020
Project Progress Summary - Week 38 - September 23, 2020
Project Progress Summary - Week 37 - September 16, 2020
Project Progress Summary - Week 36 - September 9, 2020
Project Progress Summary - Week 35 - September 2,2020
Project Progress Summary - Week 34 - August 27, 2020
Project Progress Summary - Week 33 - August 19, 2020
Project Progress Summary - Week 32 - August 13, 2020
Project Progress Summary - Week 31 - August 6, 2020
Project Progress Summary - Week 30 - July 30, 2020
Project Progress Summary - Week 29 - July 22, 2020
Project Progress Summary - Week 28 - July 16, 2020
Project Progress Summary - Week 27 - July 9, 2020
Project Progress Summary - Week 26 - July 2, 2020
Project Progress Summary - Week 25 - June 25, 2020
Project Progress Summary - Week 24 - June 17, 2020
Project Progress Summary - Week 23 - June 10, 2020
Project Progress Summary - Week 22 - June 3, 2020
Project Progress Summary - Week 21 - May 27, 2020
Project Progress Summary - Week 20 - May 20, 2020
Project Progress Summary - Week 19 - May 13, 2020
Project Progress Summary - Week 18 - May 6, 2020
Project Progress Summary - Week 17 - April 29, 2020
Project Progress Summary - Week 16 - April 22, 2020
Project Progress Summary - Week 15 - April 15, 2020
Project Progress Summary - Week 14 - April 9, 2020
Project Progress Summary - Week 13 - April 2, 2020
Project Progress Summary - Week 12 - March 26, 2020
Project Progress Summary - Week 11 - March 18, 2020
Project Progress Summary - Week 10 - March 12, 2020
Project Progress Summary - Week 9 - March 5, 2020
Project Progress Summary - Week 8 - February 26, 2020
Project Progress Summary - Week 7 - February 19, 2020
Project Progress Summary - Week 6 - February 12, 2020
Project Progress Summary - Week 5 - February 5, 2020
Project Progress Summary - Week 4 - January 30, 2020
Project Progress Summary - Week 3 - January 23, 2020
Project Progress Summary - Week 2 - January 16, 2020
Project Progress Summary - Week 1 - January 9, 2020
3 Week Look Ahead Schedules: